What Is A Permit Shot Clock
Permit shot clocks are state policies that impose a time limit for a local unit of government (LGU) to take action on a land use or building permit application. Where in place, these laws vary by state as well as by permit classification.
These state laws ensure timely action by local regulators by outlining the process of the application process, what the time limit for action is, and what the consequences for noncompliance are.
The goal with permit shot clocks can sometimes be misconceived, as the purpose is not to guarantee approval but rather to guarantee a timely decision.
Land Development Shot Clocks
Shot clocks for land use permits can range from lot-splits to new subdivisions. Examples:
Florida: Under Florida’s shot clock laws, local units of government have 30 days to consider if a development application is complete. Once deemed complete, the LGU has another 120 days to act on the project, or the permit is granted with one exception: The clock is extended to 180 days when a public hearing or quasi-judicial approval is required. Failure to act on approvals results in fee refunds, the portion of which depends on the point in the approval process. (§§ 125.022 (b) (d) and 166.033(2)(b))
Minnesota: Under §15.99, many government actions, including land use approvals, must be acted upon in Minnesota within 60 days. This same law allows parties to “toll” or pause the permit clock for an additional 60 days. If the LGU does not take action within the allotted time, the permit is considered approved.
Texas: In Texas, there is a 30-day shot clock for approvals of subdivision plats and development plans. The LGU must approve, provide conditional approval, or deny any properly submitted plan or plat within 30 days. For plans needing a resubmittal, there is a separate 15-day shot clock. After the allotted time has expired without action on a properly submitted plan, the project is approved. (§ Sec. 212.009)
Building Permit Shot Clocks
Like land use permits, shot clocks can also apply to the approval of building permits.
Examples
Arizona: For municipalities with populations of 30,000 or more, 9-470.01 gives the LGU 15 working days to approve, conditionally approve, or respond with required additions or revisions to a single-family residential building permit application (provided all the prerequisite construction documents and subdivision approvals are already in place). If the LGU does not act within that period, the required review can be performed by a qualified third-party reviewer. Under the Arizona model, the LGU cannot require the applicant to waive the statutory deadline.
Florida: Under current law 553.792, local governments generally must approve, conditionally approve, or deny a complete building permit application within:
- 30 business days for residential structures under 7,500 square feet.
- 60 business days for residential structures of 7,500 square feet or more.
- 60 business days for multifamily projects of up to 50 units.
- 12 business days for certain site-specific permits using an approved master building permit.
Impact on Housing Production
In theory, faster approvals reduce build time. A working paper from Evan Soltas and Jonathan Gruber, “How Costly Is Permitting in Housing Development?,” confirms this and demonstrates this by showing some cities complete housing construction before others can even approve a permit. In Los Angeles, for example, the paper finds that 40% of total development time is spent obtaining permits.
On Shot Clocks
“A challenge culture should be encouraged in local permitting offices by imposing ‘shot clocks’ of no more than a few weeks for permit decisions.” Stephen Slivinski, senior fellow at the Cato Institute
Considerations For Policymakers
With policymakers gravitating to this concept, there are several important considerations when seeking to enact permit shot clocks for housing:
Zoning Flexibility: The clock for land use permits starts with complete applications, meaning that permitted uses have the cleanest path for approvals. Where LGUs are reliant on discretionary or conditional approvals, too much time can be spent on negotiating before the clock starts. Minnesota, for example, has long employed the land use permit shot clock, yet permit applicants remain reliant on months, it not years, or private negotiations before the clock starts. Policymakers should ensure the flexible zoning exists if shot clocks are to be employed.
Incentives and Penalties: Some states require fee refunds or fee remittance to private party inspectors (on building permits), others require default approval. Both strategies work in encouraging timely review and should be combined. The “yes and” approach incentivizes LGU action by seeing fees refunded as well as default approvals granted.
Use Of Third Parties: On the building permit side, shot clock legislation often points to allowing third parties, or private providers, to perform the plan review and inspection services. Any legislation should be carefully written to not allow the LGU to approve a permit or inspections without providing the service, just to keep the funds. The first reason is that there are safety and durability considerations at play and these services provide a critical role in consumer protection. The second is that these fees are often imposed under a “fee-for-service” model, and without providing the service, there is no need for the fee.